Orțișoara street modernisation: 12 streets, 3,500 m signed

Orțișoara street modernisation: 12 streets, 3,500 m signed
In short

Comuna Orțișoara (Timiș county) signed on 5 November 2026 to modernise 12 existing streets in Orțișoara, Seceani and Cornești, worth 3,390,831.45 RON over 10 months. The notice states 3,500 m of street, culverts of Ø600 mm in reinforced concrete and Ø400 mm in polyethylene, road markings and signs, and geotextile on one street. It gives no count for any of them.

Comuna Orțișoara in Timiș county signed a street modernisation contract on 5 November 2026. The contractor recorded in the notice is OPREFIB CONSTRUCT 2016, with SC CLAU SPRINT CONSTRUCT SRL named as consortium member. The value is 3,390,831.45 RON, about 634,951 EUR, and the works period is 10 months.

The notice states one total: 3,500 m of street, spread over 12 streets in three villages. It also names culverts with their diameters, road markings, road signs and a geotextile layer on one street. For none of these does it state a quantity.

The notice was published on the day it was signed.

The notice states 3,500 m across three villages

The contract is notice SCNA1138922 on the public procurement portal, titled Modernizare străzi în comuna Orțișoara, județul Timiș. Its CPV code is 45233120-6, construction of roads. The description gives the length by village:

VillageStreetsLength stated
Orțișoara3457 m
Seceani82,825 m
Cornești1218 m
Total123,500 m

Seceani carries most of the length: eight of the twelve streets. The notice gives the general design values too. The design speed is 25 km/h. The carriageway is between 3.00 m and 6.00 m wide, the platform between 4.00 m and 7.00 m, and the cross slope of the carriageway is 2.5%. The pavement is a flexible structure.

The layers and the geotextile are described street by street

The works differ with the state of each street. For new construction and widening, the notice lists a wearing course of 4 cm asphalt concrete B.A. 16, a binder course of 6 cm open-graded asphalt concrete B.A.D. 22.4 and an upper foundation of crushed stone. The description we hold is cut off after that layer.

For one street, Strada 1 in Orțișoara, the notice gives a full build-up:

Strada 1 Orțișoara): Se va utiliza geotextil, urmat de straturi de uzură (4 cm BA 16) și de legătură (8 cm BAD 22.4), straturi superioare din piatră spartă (20 cm), inferioare din balast (20 cm) și un strat de formă din balast (15 cm).

In English: geotextile will be used, followed by a wearing course of 4 cm B.A. 16 and a binder course of 8 cm B.A.D. 22.4, an upper layer of 20 cm crushed stone, a lower layer of 20 cm ballast and a formation layer of 15 cm ballast. Note that the binder course is 8 cm here and 6 cm in the general description. The notice also lists streets with existing paving that is taken up. The geotextile is named for this one street only, and no area is given. A supplier of geosynthetics can read the place and the layer, not the quantity.

Culverts are named by material and diameter

On drainage, the notice states what happens to the culverts and the ditches:

Scurgerea apelor: Se vor demola și înlocui podețele existente, deteriorate, cu podețe tubulare noi din beton armat (diametru Ø600 mm pentru traseu curent) și din polietilenă (diametru Ø400 mm pentru trotuare)

In English: the existing damaged culverts will be demolished and replaced with new tubular culverts of reinforced concrete (diameter Ø600 mm for the running route) and of polyethylene (diameter Ø400 mm for the sidewalks). Existing earth ditches will be cleaned out and reprofiled, and new ditches built where needed.

This is the part most useful to a maker of drainage and precast concrete: two materials, two diameters, and which one goes where. What the notice does not state is how many culverts there are or how long each run is.

Markings and signs are named without a quantity

On traffic safety the notice says:

Siguranța circulației: Proiectul prevede realizarea de marcaje rutiere (longitudinale, transversale, inclusiv desene pe carosabil) și amplasarea de indicatoare rutiere (de avertizare, prioritate, informare)

In English: the project provides for road markings (longitudinal, transversal, including drawings on the carriageway) and for road signs (warning, priority, information). Three sign types and three marking types are named, with no count and no area. For marking and signage the notice sets the scope, not the volume. The notice names no guardrails.

Rural-roads funding, and how this notice sits in the pool

The notice says the project is financed by the European Union and the Government of Romania through the European Agricultural Fund for Rural Development, under intervention DR-28, "Crearea/Modernizarea infrastructurii rutiere de bază din spațiul rural", supplemented from the local budget. The paying agency AFIR describes DR 28 as part of the Strategic Plan for the Common Agricultural Policy 2023–2027, covering the construction, expansion and modernisation of local-interest road networks.

In our pool, 163 contracts were signed in the 30 days since 10 October 2026, and the median lag from signature to publication was 4 days. This one was published after 0 days. The evidence page shows how a notice enters the pool, with both dates.

Our article on Matca and Coronini covers two commune road contracts with far less detail. Orțișoara is the more detailed end of the same range.

The contracts in this article

NoticeContracting authorityContractorSignedValueStated in the notice
SCNA1138922COMUNA ORTISOARA (PRIMARIA ORTISOARA)OPREFIB CONSTRUCT 201605.11.20263,390,831 RON (€634,951)

Data as of 09.11.2026. Source: SICAP (e-licitatie.ro); the link opens the notice.

Frequently asked questions

How long are the streets in the Orțișoara contract?

The notice states 3,500 m in total across 12 streets. Orțișoara has 3 streets with 457 m, Seceani 8 streets with 2,825 m and Cornești 1 street with 218 m.

What does the notice say about culverts?

Existing damaged culverts are to be demolished and replaced. The new ones are tubular, of reinforced concrete at Ø600 mm for the running route and of polyethylene at Ø400 mm for the sidewalks. The notice gives no number of culverts.

Does the notice state how many road signs or how many metres of marking?

No. It names longitudinal and transversal markings, drawings on the carriageway, and warning, priority and information signs. It gives no count and no area for any of them.

Who signed the contract, and for how much?

Comuna Orțișoara signed on 5 November 2026. The contractor recorded is OPREFIB CONSTRUCT 2016, with SC CLAU SPRINT CONSTRUCT SRL named as consortium member. The value is 3,390,831.45 RON, about 634,951 EUR, with a works period of 10 months.

Sources

The current contracts are on the site

Trassa reads Romania's award notices every day: who signed, what the notice says has to be bought, and when.

See current contracts

We do not help anyone win tenders. We show you who has already won.