Curtici: ten-street asphalting contract with markings and signs

Curtici: ten-street asphalting contract with markings and signs
In short

Orașul Curtici in Arad county signed a contract on 22 October 2026 worth 2,654,495.02 RON, about 496,418 EUR, to asphalt 10 streets in the Cartier Nou district. The notice lists each street with its length, from 240.00 m to 616.00 m, and names road markings and road signs among the works without giving a quantity for either.

Orașul Curtici, a town in Arad county, signed a contract on 22 October 2026 for the asphalting of 10 streets in its Cartier Nou district. The contractor named in the notice is STRABAG. The value is 2,654,495.02 RON, about 496,418 EUR, and the works period is 15 months.

The notice was published the same day. It is unusual in one useful way: it lists every street with its length. It also says that road markings and road signs belong to the works. It gives no quantity for either, and this article keeps to that.

What was signed in Curtici

The contract is notice SCNA1138383 on the public procurement portal. It was signed and published on 22 October 2026, a lag of 0 days. The title reads Asfaltare străzi Cartier Nou in the town of Curtici, Arad county. The notice's CPV code is 45233140-2, road works.

The description ties the cost to chapter 4 of the investment budget, basic investment, item 4.1, construction and installations. The text we hold names no funding programme, and we do not guess one.

The notice lists ten streets and a length for each

The description states that the works cover asphalting of a number of 10 streets in the town. Each comes with a length:

StreetLength stated in the notice
Strada Ion Creangă616.00 m
Strada Ștefan Augustin Doinaș583.00 m
Strada Virgil Iovănaș491.00 m
Strada I. C. Brătianu303.00 m
Strada Ioan Slavici294.00 m
Strada Iuliu Maniu278.00 m
Strada Independenței249.00 m
Strada Nelu Aristide Dragomir244.00 m
Strada Regele Ferdinand243.00 m
Strada Regina Maria240.00 m

The notice misspells the first word of the fifth street, "Ioan Slavici"; we write the name as it is meant. The longest street is Strada Ion Creangă at 616.00 m, the shortest Strada Regina Maria at 240.00 m. We do not add the ten lengths: the notice gives no total, and a sum of our own would not be a figure the notice states.

The works the notice names

The description sets out what the contract covers:

Obiectul contractului îl constituie execuția lucrărilor de modernizare a infrastructurii rutiere aferente obiectivului de investiții „Asfaltare Străzi Cartier Nou”, incluzând lucrări de terasamente, realizarea structurii rutiere, execuția îmbrăcăminților asfaltice, amenajarea drumurilor laterale, executarea marcajelor și montarea indicatoarelor rutiere, conform Proiectului Tehnic de Execuție astfel:

In English: the contract covers modernisation of the road infrastructure of the "Asfaltare Străzi Cartier Nou" investment, including earthworks, the road structure, asphalt surfacing, the arrangement of side roads, the execution of road markings and the installation of road signs, as set out in the technical execution design.

Two of those items are products a supplier sells. Executarea marcajelor means road markings; montarea indicatoarelor rutiere means the mounting of road signs. The notice states neither a length of marking nor a number of signs. Those would be in the technical execution design, which the notice cites but we do not hold. Earthworks, road structure and surfacing are named without any quantity either.

For a supplier of road marking and signs, the notice gives a place, ten named streets and a works period of 15 months. It does not give a bill of quantities.

Where this sits among recent contracts

Curtici is one of 168 contracts in our pool signed since 28 September 2026. Across those, the median lag from signature to publication is 4 days, so this notice appeared ahead of the median. We covered three other local-road contracts, one of which also names signs, markings and parapets in a single sentence, in an earlier article. The evidence page shows how a notice enters our pool, with the dates of signature and publication.

The notice text refers to Law no. 98/2016 on public procurement, in its provisions on clarification requests. The law was published in Monitorul Oficial no. 390 of 23 May 2016, and its text is on the legislative portal.

The contracts in this article

NoticeContracting authorityContractorSignedValueStated in the notice
SCNA1138383Orasul CurticiSTRABAG22.10.20262,654,495 RON (€496,279)

Data as of 28.10.2026. Source: SICAP (e-licitatie.ro); the link opens the notice.

Frequently asked questions

How many streets does the Curtici asphalting contract cover?

The notice states 10 streets in the Cartier Nou district of Curtici, Arad county, each with a length between 240.00 m and 616.00 m. It gives no total length.

Does the notice state a quantity of road markings or signs?

No. It names the execution of road markings and the installation of road signs among the works, but gives no length of marking and no number of signs. Quantities would be in the technical execution design, which the notice refers to.

Who signed the contract, and for how much?

Orașul Curtici signed on 22 October 2026 with the contractor STRABAG. The value recorded is 2,654,495.02 RON, about 496,418 EUR, with a works period of 15 months.

Does the notice say who will supply the markings and signs?

No. The notice describes works and says nothing about suppliers. We do not guess.

Sources

The current contracts are on the site

Trassa reads Romania's award notices every day: who signed, what the notice says has to be bought, and when.

See current contracts

We do not help anyone win tenders. We show you who has already won.